Vegetarian Treatment
1, based on cement powder or grindstone,
2. The vegetarian ground needs to be kept for more than 28 days, and the moisture content should be less than 8%.
3, Make up the ground with epoxy mortar;
4, The oil pollution in the plain is clean and clean.
5, Before construction, it is necessary to keep the construction site dry and clean.

Bottom Coating
1. Before construction, it is necessary to keep clean. If impurities are adhered, the main agent and hardener should be mixed in proper proportion and fully stirred.
2, Second, it is necessary to adjust the proper viscosity and finish the material within 4 hours according to the ground conditions.
3, The time of curing and hardening of the bottom coating is more than 8 hours.

Medium Coating
1. Before construction, it is necessary to keep clean. If impurities are adhered, the main agent and hardener should be mixed in proper proportion and fully stirred.
2.adding proper amount of resin to the quartz sand.
3, The material is evenly coated with a trowel.
4,the mixture should be completed within 30 minutes.
5, handover at the junction of construction;
6, The time of curing and hardening of the medium coating is more than 8 hours.

Batch Coating
1. Mix the main agent and hardener in proper proportion and stir well.
2, The material is evenly coated by using a batch knife.
3, the completion of the mixed material should be completed within 30 minutes.
4, the time of curing and hardening of the soil was more than 8 hours.
5, according to the actual needs, the construction requirements of the construction must be smooth and no holes, and no batch cutter and sand print shall prevail.

Surface Coating
1. Keep clean before construction;
2, Second, the pre - mixing of the main agent;
3, Third, mix the main agent and hardener in the right proportion and stir well.
4, use the roller or trowel to evenly coat the material and complete the material in 30 minutes.
5, It is necessary to handle the handover at the junction of the construction.
6, After construction is completed, it can be taken 24 hours later, and can be repressed after 72 hours (with 250C as the standard, and the opening time at low temperature should be extended moderately).